The Building Safety (Remediation of Unsafe Cladding etc) Bill: an overview for owners, managers and residents
On 14 October 2026 the government published its guide to the Building Safety (Remediation of Unsafe Cladding etc) Bill. The Bill would introduce a legal duty on the owners of certain residential buildings in England to assess and remediate unsafe cladding. It is still a Bill and is not yet law, and much of the detail will be set out in regulations.
Who it covers
The duty would apply to multi-occupied residential buildings in England that are over 11 metres tall or have at least five storeys, and that were completed before 28 June 2022. Private and social housing are both in scope, including enfranchised and commonhold blocks.
The main exception is buildings already covered by the Developer Remediation Contract. The 53 developers who have signed it have committed to assess and fix life-critical fire safety defects, so those buildings sit outside the new duty.
The duty would fall on whoever holds the repairing obligation, which the guide calls the responsible entity. This could be a freeholder, a head or sub-leaseholder, a right to manage company or a resident management company.
What the Bill requires
The Bill sets out three steps, each backed by a legal duty.
Assess. Where a general fire risk assessment recommends it, a fire risk assessment of the external walls (FRAEW) is required, following PAS 9980, the British Standards Institution method already widely used in the industry. Assessments carried out since 16 May 2022 do not need repeating if they met the rules at the time. Homes England will audit every FRAEW that recommends work, along with a share of those that conclude none is needed.
Plan. If a FRAEW recommends work, the owner must publish a Remediation Compliance Plan. The plan sets out the steps and timetable, names the responsible director, and lists beneficial owners and the wider company group. It is published on the owner’s website and provided to residents and leaseholders. The cost of producing it cannot be passed on to leaseholders.
Remediate. Owners must carry out the FRAEW recommendations, and any interim measures, as soon as reasonably practicable. Interim measures such as waking watch are temporary, are not a substitute for remediation, and must be stood down once the building is remediated.
Key dates
All dates run from Royal Assent, for which there is not yet a date.
|
When
|
What happens
|
|
2 months after Royal Assent
|
The duties to assess, mitigate and remediate begin, along with the new regulator powers, the manufacturer claim changes and the rules on regulator co-operation
|
|
About 6 months
|
Regulations on how backstop notices are served, plus guidance on Remediation Management Orders
|
|
About 8 to 10 months
|
Rules for the 11 to 18 metre building register expected
|
|
12 months
|
Deadline to assess. Enforcement for failing to assess can begin
|
|
15 months
|
Deadline to publish a Remediation Compliance Plan
|
Smaller changes worth knowing about
-
Ownership information. Local housing authorities, fire and rescue authorities, the Building Safety Regulator and Homes England will be able to demand details of who owns and controls a block, including beneficial owners.
Preparing in advance
Responsible entities may find it useful to start preparing before Royal Assent. The department has said it will publish draft guidance before the duties start, followed by regulations on what counts as a required remediation step.